It is currently Tue Sep 23, 2014 6:31 pm
   
Text Size

NTK Work Day List

Information & questions about the NTK club organization and track.

Moderator: Kevin Crowe

NTK Work Day List

Postby Yaani-Mai Gaddy » Tue Mar 02, 2010 12:19 pm

NTK Work Day List

Here is a list of repair and maintenance items that need attention at the track. The next work day is April 3rd. Help keep the track safe and in good repair. Join us on April 3rd for the work day & earn membership renewal credits.

If you would like to complete any of these jobs on a non work day & receive work day credits please contact Bob Schabel at 972-221-2567.

- Pick up and empty trash
- Clean Farmers Field
- Fill new Crash Bags with foam
- Crush some White plastic Barrels and throw in trash
- Sponsor parking signs need to be posted
- Pit runner needs to be re-striped
- Spread Fire Ant Killer
- Straighten tires and barrels around track, Clear weeds form under barrels
- Check bathroom for supplies, Clean if necessary
- Fix any urinal valves in the restrooms that are stuck
- Fix men’s toilet that runs
- Woman’s restroom needs toilet seat replaced
- Install Shelves in electronics room
- Sweep pit runner
- Sweep out tech barn
- Make sure sponsor signs are OK / Hang sponsor signs
- Check the heat lamp that is running to the well house. (Winter months only)
- Mount LAN Hub in Radio room
- Complete installation of security system
- Fix 2 cameras not working on tech barn. Install camera on tech barn
- Design better system to hang Sponsor Signs
- Finish floor on second floor, install railing
- Fix light & connections on light pole by electric utility box on west fence
- Fix lights on Pit Runner, first bank won’t turn on (need breakers?)
- Fix Lights on pole between turn 1 and 2
- Fix lights on pole in infield by cutoff
- Fix light on pit runner
- Replace security light bulbs that are burned out
- Fix conduit on light pole outside of fence on back between turn 1 and 9
- Get radio for Scoring Tower
- Bury conduit & pull 220/110 lines for well house (John Ray)
- Terminate conduit near scoring tower and cut off post (John Ray)
- Fix Bathroom Rain Gutter (Bob & Gutter contractor)
- Drill & bore hole under track exit ramp for conduit and wire. Set pole by grid
- Install Front Gate opener and controls
- Fix Hot Pit Concrete
- Add concrete on left side of Tech Barn Driveway
- Install new drainage lines along tech barn
- Move fence along Turn 1-2 straight back towards well house/shed
- Repair fence gate by turn 1 so it closes
- Get 2 12 yards of screen top soil, dump outside fence by turn 1
- Build Printer stand for Gate House
- Build Security System Stand for Gate House
- Fix electrical extensions in gate house (need plugs female)
- Install air compressor and air lines
- Make chain link fence road Harrow/groomer
- Assemble current 2010 rulebooks for NTK, Rotax, TAG, 2008 KART. Three
copies for Scoring, Tech director, and Race Director

If you would like to complete any of these jobs on a non work day & receive work day credits please contact Bob Schabel at 972-221-2567.
Yaani-Mai Gaddy
www.gaddywebdesign.com
972-462-8393
Yaani-Mai Gaddy
NTK Member
 
Posts: 634
Joined: Thu Aug 10, 2006 1:59 pm

Return to NTK Track Forum

Who is online

Users browsing this forum: No registered users and 1 guest


Who is online

In total there is 1 user online :: 0 registered, 0 hidden and 1 guest (based on users active over the past 5 minutes)
Most users ever online was 168 on Wed Jul 04, 2012 1:25 am

Users browsing this forum: No registered users and 1 guest

Login Form